Template:M summ 2002 ISDA 5(b)(i)
A comparison between the 1992 ISDA and the 2002 ISDA can be found on the ISDA Comparison page.
Illegality vs. Force Majeure smackdown
Like a Force Majeure Event, an Illegality may only be triggered after exhausting the fallbacks and remedies specified in the 2002 ISDA.
Hierarchy of Events
Under the 2002 ISDA, Section 5(c) intervenes to provide that (i) Illegality trumps Force Majeure and Illegality and Force Majeure trump Failure to Pay and Breach of Agreement. Given that Illegality is no longer subject to the "two Affected Parties" delay on termination (as it was in the 1992 ISDA), this is significant.