Pre-Estimate - ISDA Provision

Revision as of 18:36, 9 January 2018 by Amwelladmin (talk | contribs)
ISDA Anatomy™


2002 ISDA

6(e)(v) Pre-Estimate. The parties agree that an amount recoverable under this Section 6(e) is a reasonable pre-estimate of loss and not a penalty. Such amount is payable for the loss of bargain and the loss of protection against future risks, and, except as otherwise provided in this Agreement, neither party will be entitled to recover any additional damages as a consequence of the termination of the Terminated Transactions.

(view template)

1992 ISDA
6(e)(iv) Pre-Estimate. The parties agree that if Market Quotation applies an amount recoverable under this Section 6(e) is a reasonable pre-estimate of loss and not a penalty. Such amount is payable for the loss of bargain and the loss of protection against future risks and except as otherwise provided in this Agreement neither party will be entitled to recover any additional damages as a consequence of such losses.

(view template)

Index: Click to expand:Navigation
See ISDA Comparison for a comparison between the 1992 ISDA and the 2002 ISDA.
The Varieties of ISDA Experience
Subject 2002 (wikitext) 1992 (wikitext) 1987 (wikitext)
Preamble Pre Pre Pre
Interpretation 1 1 1
Obligns/Payment 2 2 2
Representations 3 3 3
Agreements 4 4 4
EODs & Term Events 5 Events of Default: FTPDBreachCSDMisrepDUSTCross DefaultBankruptcyMWA Termination Events: IllegalityFMTax EventTEUMCEUMATE 5 Events of Default: FTPDBreachCSDMisrepDUSTCross DefaultBankruptcyMWA Termination Events: IllegalityTax EventTEUMCEUMATE 5 Events of Default: FTPDBreachCSDMisrepDUSSCross DefaultBankruptcyMWA Termination Events: IllegalityTax EventTEUMCEUM
Early Termination 6 Early Termination: ET right on EODET right on TEEffect of DesignationCalculations; Payment DatePayments on ETSet-off 6 Early Termination: ET right on EODET right on TEEffect of DesignationCalculationsPayments on ETSet-off 6 Early Termination: ET right on EODET right on TEEffect of DesignationCalculationsPayments on ET
Transfer 7 7 7
Contractual Currency 8 8 8
Miscellaneous 9 9 9
Offices; Multibranch Parties 10 10 10
Expenses 11 11 11
Notices 12 12 12
Governing Law 13 13 13
Definitions 14 14 14
Schedule Schedule Schedule Schedule
Termination Provisions Part 1 Part 1 Part 1
Tax Representations Part 2 Part 2 Part 2
Documents for Delivery Part 3 Part 3 Part 3
Miscellaneous Part 4 Part 4 Part 4
Other Provisions Part 5 Part 5 Part 5