5(b) Termination Events. The occurrence at any time with respect to a party or, if applicable, any Credit Support Provider of such party or any Specified Entity of such party of any event specified below constitutes an Illegality if the event is specified in (i) below, a Tax Event if the event is specified in (ii) below or a Tax Event Upon Merger if the event is specified in (iii) below, and, if specified to be applicable, a Credit Event Upon Merger if the event is specified pursuant to (iv) below or an Additional Termination Event if the event is specified pursuant to (v) below:—
5(b)(i) Illegality. Due to the adoption of, or any change in, any applicable law after the date on which a Transaction is entered into, or due to the promulgation of, or any change in, the interpretation by any court, tribunal or regulatory authority with competent jurisdiction of any applicable law after such date, it becomes unlawful (other than as a result of a breach by the party of Section 4(b)) for such party (which will be the Affected Party):
5(b)(i)(1) to perform any absolute or contingent obligation to make a payment or delivery or to receive a payment or delivery in respect of such Transaction or to comply with any other material provision of this Agreement relating to such Transaction; or
5(b)(i)(2) to perform, or for any Credit Support Provider of such party to perform, any contingent or other obligation which the party (or such Credit Support Provider) has under any Credit Support Document relating to such Transaction;
5(b)(ii) Tax Event.[1] Due to:
(x) any action taken by a taxing authority, or brought in a court of competent jurisdiction, on or after the date on which a Transaction is entered into (regardless of whether such action is taken or brought with respect to a party to this Agreement) or
(y) a Change in Tax Law,
the party (which will be the Affected Party) will, or there is a substantial likelihood that it will, on the next succeeding Scheduled Payment Date
(1) be required to pay to the other party an additional amount in respect of an Indemnifiable Tax under Section 2(d)(i)(4) (except in respect of interest under Section 2(e), 6(d)(ii) or 6(e)) or
(2) receive a payment from which an amount is required to be deducted or withheld for or on account of a Tax (except in respect of interest under Section 2(e), 6(d)(ii) or 6(e)) and no additional amount is required to be paid in respect of such Tax under Section 2(d)(i)(4) (other than by reason of Section 2(d)(i)(4)(A) or (B));
5(b)(iii) Tax Event Upon Merger. The party (the “Burdened Party”) on the next succeeding Scheduled Payment Date will either (1) be required to pay an additional amount in respect of an Indemnifiable Tax under Section 2(d)(i)(4) (except in respect of interest under Section 2(e), 6(d)(ii) or 6(e)) or (2) receive a payment from which an amount has been deducted or withheld for or on account of any Indemnifiable Tax in respect of which the other party is not required to pay an additional amount (other than by reason of Section 2(d)(i)(4)(A) or (B)), in either case as a result of a party consolidating or amalgamating with, or merging with or into, or transferring all or substantially all its assets to, another entity (which will be the Affected Party) where such action does not constitute an event described in Section 5(a)(viii);
5(b)(iv) Credit Event Upon Merger. If “Credit Event Upon Merger” is specified in the Schedule as applying to the party, such party (“X”), any Credit Support Provider of X or any applicable Specified Entity of X consolidates or amalgamates with, or merges with or into, or transfers all or substantially all its assets to, another entity and such action does not constitute an event described in Section 5(a)(viii) but the creditworthiness of the resulting, surviving or transferee entity is materially weaker than that of X, such Credit Support Provider or such Specified Entity, as the case may be, immediately prior to such action (and, in such event, X or its successor or transferee, as appropriate, will be the Affected Party); or
5(b)(v) Additional Termination Event. If any “Additional Termination Event” is specified in the Schedule or any Confirmation as applying, the occurrence of such event (and, in such event, the Affected Party or Affected Parties shall be as specified for such Additional Termination Event in the Schedule or such Confirmation).

Related agreements and comparisons

Related Agreements
Click here for the text of Section 5(b) in the 2002 ISDA
Comparisons
Click to compare this section in the 1992 ISDA and 2002 ISDA.

Comments? Questions? Suggestions? Requests? Insults? We’d love to 📧 hear from you.
Sign up for our newsletter.

Content and comparisons

Trick for young players: Force Majeure Event

Note that the 2002 ISDA includes a Force Majeure Event, using language that was already agreed and widely inserted into the 1992 ISDA Schedule prior to its publication. Because this was entered as Section 5(b)(ii), this necessitates some numbering differences between the two versions of the ISDA Master Agreement — a drafting trick for young players to watch out for.

Template

Summary

Template:M summ 1992 ISDA 5(b)

Template

General discussion

Template:M gen 1992 ISDA 5(b)

Template

See also

Template:M sa 1992 ISDA 5(b)

Template

References

  1. The line breaks are for comprehension and do not appear in the original