Waiting Period - ISDA Provision

From The Jolly Contrarian
Jump to navigation Jump to search
2002 ISDA Master Agreement

A Jolly Contrarian owner’s manual™

Waiting Period in a Nutshell

The JC’s Nutshell summary of this term has moved uptown to the subscription-only ninja tier. For the cost of ½ a weekly 🍺 you can get it here. Sign up at Substack.

Waiting Period in all its glory

Waiting Period” means:―
(a) in respect of an event or circumstance under Section 5(b)(i), other than in the case of Section 5(b)(i)(2) where the relevant payment, delivery or compliance is actually required on the relevant day (in which case no Waiting Period will apply), a period of three Local Business Days (or days that would have been Local Business Days but for the occurrence of that event or circumstance) following the occurrence of that event or circumstance; and
(b) in respect of an event or circumstance under Section 5(b)(ii), other than in the case of Section 5(b)(ii)(2) where the relevant payment, delivery or compliance is actually required on the relevant day (in which case no Waiting Period will apply), a period of eight Local Business Days (or days that would have been Local Business Days but for the occurrence of that event or circumstance) following the occurrence of that event or circumstance.

Related agreements and comparisons

Click here for the text of Section Waiting Period in the 1992 ISDA
There is no “Waiting Period” in the 1992 ISDA

Resources and Navigation

This provision in the 1992

Resources Wikitext | Nutshell wikitext | 1992 ISDA wikitext | 2002 vs 1992 Showdown | 2006 ISDA Definitions | 2008 ISDA | JC’s ISDA code project
Navigation Preamble | 1(a) (b) (c) | 2(a) (b) (c) (d) | 3(a) (b) (c) (d) (e) (f) (g) | 4(a) (b) (c) (d) (e) | 55(a) Events of Default: 5(a)(i) Failure to Pay or Deliver 5(a)(ii) Breach of Agreement 5(a)(iii) Credit Support Default 5(a)(iv) Misrepresentation 5(a)(v) Default Under Specified Transaction 5(a)(vi) Cross Default 5(a)(vii) Bankruptcy 5(a)(viii) Merger Without Assumption 5(b) Termination Events: 5(b)(i) Illegality 5(b)(ii) Force Majeure Event 5(b)(iii) Tax Event 5(b)(iv) Tax Event Upon Merger 5(b)(v) Credit Event Upon Merger 5(b)(vi) Additional Termination Event (c) (d) (e) | 6(a) (b) (c) (d) (e) (f) | 7 | 8(a) (b) (c) (d) | 9(a) (b) (c) (d) (e) (f) (g) (h) | 10 | 11 | 12(a) (b) | 13(a) (b) (c) (d) | 14 |

Index: Click to expand:

Overview

edit

There is no “Waiting Period” in the 1992 ISDA. ISDA’s crack drafting squad™ introduced it in the 2002 ISDA with the arrival of Force Majeure, and liked it so much they extended it to Illegality.

Summary

edit

The point of Waiting Period is, for potential scenarios that might wind up justifying termination later, but you don’t yet know that, to build in a period to wait and see. For Illegality events (Section 5(b)(i)) is three Local Business Days — it is not so likely that an Illegality will sort itself out; for a Force Majeure Event (5(b)(ii) — where insh’Allah, things will come right and everyone can eventually go back to what they were doing, it is eight Local Business Days.

Waiting Periods — as defined in the ISDA Master Agreement also sometimes show up sometimes in other booklets — for example, ISDA’s Emissions Annex.

Through the good offices of Section 5(d), payments and deliveries which otherwise would be due during a Waiting Period are suspended.

Premium content

Here the free bit runs out. Subscribers click 👉 here. New readers sign up 👉 here and, for ½ a weekly 🍺 go full ninja about all these juicy topics 👇
  • The JC’s famous Nutshell summary of this clause
  • Waiting Period as a further source of indeterminacy around Section 2(a)(iii)
edit

See also

edit

References